ZTELEC Delivers Custom 11MVA Oil-Immersed Mining Transformers to Armenia

2026-11-12 0 Comments

ZTELEC, a global manufacturer of IEC-standard power transformers, has completed and shipped two custom oil-immersed mining transformers to a mining operation in Armenia.

Each unit is rated 11 MVA, 10 kV. Both are engineered to power ABB ACS 6000 medium-voltage variable frequency drive (VFD) systems and fully comply with the IEC 60076 international transformer standard.

This project shows how a purpose-built mining transformer can keep critical production equipment running in some of the toughest operating environments in the industry.

11MVA 10kV transformer

Project Overview at a Glance

The table below summarizes the key specifications of this Armenia mining transformer delivery.

Item Details
Product Custom oil-immersed mining transformer
Quantity 2 sets
Rated capacity 11 MVA
Voltage level 10 kV
Winding material Aluminum
Standard IEC 60076
Matched drive system ABB ACS 6000 medium-voltage VFD
Application Mountain mining site, Armenia
Lead time 2 months

Built for ABB ACS 6000 VFD Systems

Mining concentrators and grinding mills driven by ACS 6000 VFDs place special demands on the transformers that feed them.

Variable-frequency loads create harmonic currents and fluctuating load profiles that a generic distribution transformer is not designed to handle.

ZTELEC tuned this oil-immersed mining transformer to work seamlessly with the ACS 6000 drive platform. The result is a steady power supply and a lower risk of unexpected downtime in remote mountain mines.

For mine operators, every hour of unplanned stoppage in the grinding circuit means lost throughput. A transformer matched to the drive from the start is one of the simplest ways to protect that output.

Why Mountain Mining Sites Need Reinforced Transformers

Highland mine sites are tough on electrical equipment. Unlike standard distribution transformers, these units feature a reinforced mechanical structure designed for three common stress factors.

Continuous Mechanical Vibration

Crushers, mills and heavy haulage generate constant vibration. Over time, this can loosen connections and fatigue core and winding supports.

The anti-vibration design of these transformers strengthens the internal clamping and structural support to resist this wear.

Heavy Dust Pollution

Mine dust settles on bushings, radiators and enclosures. It can reduce insulation performance and impair cooling.

A dust-proof design helps keep surfaces and cooling paths functioning, and reduces the cleaning and inspection workload for on-site crews.

Wide Ambient Temperature Fluctuations

Mountain climates can swing sharply between day and night and between seasons. Oil volume, insulation materials and sealing must cope with these changes.

A wide-temperature design supports stable operation and helps extend service life.

Aluminum Windings for Stable Power Conversion

This batch of mining transformers uses aluminum windings. Aluminum is widely used in oil-immersed power transformers because it offers a good balance of electrical performance, weight and cost.

Combined with a robust core and coil structure, aluminum windings deliver stable power conversion and distribution for the mine's core production equipment.

For large projects with strict budgets and tight schedules, winding material selection is an important design decision. ZTELEC engineers can advise on aluminum or copper options based on each project's requirements.

IEC 60076 Compliance and Factory Acceptance Testing

IEC 60076 is the international series of standards for power transformers. It covers ratings, temperature rise, insulation levels and testing procedures.

Building to this standard gives mine owners, EPC contractors and consultants a clear, internationally recognized basis for design review and acceptance.

Before dispatch, both transformers went through complete factory acceptance testing (FAT). This step confirms that each unit performs as specified before it leaves the factory, and it reduces commissioning risk at a remote site where rework is expensive and slow.

A Full Turnkey Engineering Package

ZTELEC supplied a complete turnkey package for this Armenia mining project. The scope included:

Customized design. Electrical and mechanical design tailored to the drive system and the mine's site conditions.

Precision manufacturing. Controlled production processes for the core, windings and tank.

Complete FAT. Full factory testing before shipment.

Matching accessories. All required accessories supplied together with the transformers.

Having a single supplier responsible for design, manufacturing, testing and accessories simplifies coordination and shortens the path from order to energization.

Delivered Within a 2-Month Lead Time

Custom mining transformers often involve long lead times because of special design requirements. For this project, the mine's construction schedule left little room for delay.

Despite the strict custom requirements, ZTELEC completed the project within a 2-month lead time to match the construction timeline.

Early technical alignment, efficient engineering and well-organized production made this possible.

oil-immersed mining transformer

What ZTELEC's Engineers Say

"Mine transformers for large VFD loads cannot rely on generic designs. Every mountain mining site brings unique environmental and electrical challenges. Our custom solution balances IEC compliance, rugged mechanical build and stable performance for variable-frequency mining loads."

— Lead Transformer Engineer, ZTELEC

How to Choose a Mining Transformer for VFD Loads

If you are planning a similar project, these are the main points to review with your transformer supplier.

Match the Transformer to the Drive

Share the drive model, configuration and load profile early. VFD-duty transformers may need specific winding arrangements and harmonic considerations that depend on the drive platform.

Define Site Conditions Clearly

Provide altitude, ambient temperature range, dust level and expected vibration. These data points drive decisions on insulation, cooling, sealing and structural design.

Confirm Standards and Testing

Specify the applicable standard, such as IEC 60076, and agree on the test program, including factory acceptance testing, before manufacturing begins.

Plan the Schedule Backwards

Work back from your construction milestones and confirm the supplier's realistic lead time for custom engineering, production, testing and transport.

Frequently Asked Questions

What is an oil-immersed mining transformer?

It is a power transformer whose core and windings are immersed in insulating oil for cooling and insulation. It is built with a reinforced structure to suit the demanding conditions of mine sites.

Can ZTELEC customize transformers for ABB ACS 6000 drives?

Yes. ZTELEC designs custom oil-immersed transformers for VFD applications and has delivered units matched to the ABB ACS 6000 platform.

Which standard do these transformers follow?

The transformers in this project comply with the IEC 60076 international transformer standard.

Is aluminum or copper better for transformer windings?

Both are widely used. The best choice depends on project requirements such as efficiency targets, size, weight and budget. ZTELEC engineers can recommend the right option for your application.

Can you supply transformers for high-altitude or dusty mine sites?

Yes. ZTELEC engineers custom designs for high-vibration, dusty and wide-temperature environments, including high-altitude mining locations.

About ZTELEC

This Armenia delivery adds another proven mining reference to ZTELEC's global project portfolio.

The company supplies customized oil-immersed transformers, compact substations and high-voltage switchgear for mining, renewable energy and heavy industrial markets worldwide.

Request an Engineering Proposal and Quotation

Do you need IEC oil-immersed mining transformers tailored for VFD loads, or for dusty, high-vibration or high-altitude mine sites?

Contact ZTELEC today with your drive model, rated capacity, voltage level and site conditions. Our engineering team will prepare a detailed technical proposal and quotation for your project.

Request for Quotation

Contact for Quotation